- Design + selections: 2-6 weeks (longer if you want custom everything)
- Permits (if needed): timeline varies by scope and jurisdiction
- Ordering lead times: 2-10+ weeks depending on cabinets, counters, and specialty items
- Construction: 4-8+ weeks for most full remodels (scope dependent)
What causes delays most often
- Late decisions on finishes (tile, hardware, fixtures)
- Backordered cabinets or appliances
- Discoveries behind walls (old wiring, plumbing surprises, water damage)
- Change orders after demolition
The fix is not “rush.” The fix is “decide early.” A good team will provide a selection schedule so you are never making critical choices at the last minute.